Post 3 Energy 21/01/2026.
Teuana mai buakon oin taben te Botaki ni Mwakuri ibukin Mwakurian Karikirake ao kateimatoan korakora, bon tararuan te iti, imwain kamaiuakina bwa ena mano man kanganga.
N te bong aio 21/01/2026, ao e mwananga temanna ae e onimakinaki man te Energy Planning Department ni karaoa tabena ibukin tuoakin te iti imwain karokoana n te mwenga teuana iaon Eita, Tarawa, ao e noraki ao ni kakoauaki bwa taan mwakuria te iti aio, bon te Contractor, ake a bane n tia n reke ke ni iai aia licenses, ibukin mwakurian te iti, katomakina bwa ana mano wire ake a kabonganaki, ao a mwaiti riki.
Iai tabeua kanganga ake a noraki inanon te tutuo aio, are e kaineti ma wire ake a kabonganaki inanon te meter box are ngaia oin te iti inanon te mwenga aio are e katitiki man te Baokin te Iti bwa iai aika ana oneaki mai iai.
Ma irarikin anne, ao e tuai kona ni kabongana te iti te auti aio, ni karokoa e kakoroi nanon baika a noraki bwa ana riai ni katamaroaki riki imwin te tutuo aio.
E rangi ni mwaiti auti aika e karaoaki te tutuo (Inspection) nako iai, ma taran te ribooti ae e noraki bwa tabeua mai ibuakoia, a bane n tuai moa kona n toma ngke ni karokoaki aia itii ni karokoa a bane n toamau bwaai ni kabane ake a noraki bwa ana riai ni karaoa te onono ma te mwakuri ni katamaroa nako iai.
Aikai waaki ma mwakuri aika e teimatoa ni karaoaia te Botaki ni Mwakuri, ibukin tobwakin kanganga ma kanakoraoan mwakurian te iti bwa ena mano nakoia te Botannaomata.
Te kantaninga raoi, bwa e riai te Botannaomata ni moanibwaia ke ni ira raoi ana kainibaire te iti, ibukin manon te mwenga ao manoia te botannaomata.
...............................................................................................................................................
One of the major responsibilities of the Ministry of Infrastructure and Sustainable Energy is to oversee the electricity sector to ensure safety, reliability, and the prevention of operational challenges.
This week, a senior staff member from the Energy Department inspected Eita, and it was confirmed that the meter box installed by the contractor was registered under the Ministry’s regulations and had the required work permits.
The inspection officer noted several minor issues with the wiring in the meter box installation. The meter box, which serves as the main connection point between the household and the PUB-supplied public electricity supply, must be renewed.
Therefore, the household is not permitted to use electricity until all the requirements and issues identified by the inspection officer have been addressed.
The EPD inspector inspects many households, but some are not allowed to use electricity until the inspector’s concerns have been resolved.
This demonstrates the important role of the Ministry in preventing problems before households are connected to electricity, ensuring safety for the community.