Divisions Activities Progress
Energy Sector

Improve fuel shipment to fill up prefab/ISO tanks in the OIs using among others, a new Tanker in the medium term and thus do away with using drums (Implementation - Ph II)

41
Ennergy Sector

Review of the ISO vs T55 tanks options for the Ois and adopt for Ois Fuel storage - Phase II

100
Ennergy Sector

Increase storage capacity to keep up with rapid increase in demand by installation of prefab-tanks/ISO tanks in the OIs - phase 2

61
Ennergy Sector

Initiating solarization of MISE HQ

61
Ennergy Sector

Sign contract and comencement of feasibility study for Marakei and Makin solar mini-grid systems

21
Ennergy Sector

Work with communities to seek funding for solar systems to be installed on their church buildings

100
Ennergy Sector

Available stock on spare parts for the Chinese donated household solar lights

100
Ennergy Sector

Installation of 16KW solar system on the first-three selected islets which are Takuu, Aiwa and Tenatorua

21
CED

Conduct survey for feeder roads on South Tarawa (Arorae island and S/Tarawa Acess Road)

41
CED

Bless the newly arrived MISE 5 sets of heavy machines supplied by Big D

100