Divisions Activities Progress
CED

Obtain EIA for ISTTNSP (China Aid to Improvement to South Tarawa Transport Network System Project)

100
CED

Concept designs and cost estimate for causeways to be available for KOITIIP selected islands

100
CED

Scope the rehabilitation of Causeways on Beru, Nonouti, and Tab South islands

100
CED

PVU to replace 1 GoK vehicle and purchase 1 heavy machine (front loader)

81
CED

Progress PVU reform

81
CED

Complete maintenance work to Onotoa causeway 

81
CED

Secure the EIA consultant for Tab North and Nikunau road and causeway

61
CED

Sign the agreement for MISE material testing laboratory (TA support)

81
CED

Process procurement of medium size machines for remain islands under phase 2

81
CED

Deliver all medium size machines to 12 selected islands under phase 1

100